Ten years on from Kaikōura: Reflections on critical rebuild of key freight route
Saturday 14 November marks the 10th anniversary of the biggest rail rebuild in New Zealand's history. Customers, KiwiRail team members, transport agencies and community groups will be reflecting on its significance.
When the Kaikōura earthquake struck on 14 November 2016, one of New Zealand’s key freight corridors was severed overnight.
The 7.8 magnitude earthquake caused unprecedented damage to the Main North Line between Picton and Christchurch. Almost 60 major damage sites and 750 individual sites needed repair, including tunnels, bridges and embankments.
Before the earthquake, more than one million tonnes of freight moved along it each year.
For customers, the impact was immediate. With rail and State Highway 1 cut, freight bound for Canterbury and further south had to shift to road and take longer inland routes.
Tony Bascik, Director of Bascik Transport said at the time “KiwiRail are giving it everything and I’m very impressed with progress. We’ve had to set up a roading link between Christchurch and Blenheim – there’s obviously a lot of extra cost in that, a lot of extra effort, but we value our relationship and look forward to the line reopening.”
Keeping customers moving
KiwiRail’s focus through the rebuild was on finding solutions and keeping customers informed.
“Our priorities were maintaining constant engagement with customers and doing everything possible to keep freight moving,” remembers KiwiRail General Manager Freight Markets Alan Piper.
KiwiRail established the NZ Connect service together with the Port of Auckland, shipping line ANL/CMA CGM and Lyttelton Port, providing coastal capacity between Auckland and Christchurch. The Spring Creek freight hub near Blenheim was also expanded to support freight forwarders while the railway remained closed.
Grant Lemin, then General Manager of Toll (now Team Global Express) commented on the massive operation, “We’ve had to put a lot of extra trucks and drivers on. It’s great to see the progress being made, particularly for rail. Road has a long way to go.”
The return of rail and building back stronger
Just 10 months after the earthquake, rail freight was moving through Kaikōura again.
The first freight train travelled the reopened Main North Line on 15 September 2017, restoring a critical rail connection between the upper South Island and Canterbury.
Services initially ran at night while the wider recovery continued, with daytime freight returning in October 2018.
The recovery wasn’t just about reopening the Main North Line. It was about rebuilding with more resilience, including slope stabilisation, debris barriers, seawalls, monitoring systems and new operational controls to protect the corridor from future slips and severe weather.
The experience also strengthened KiwiRail’s wider emergency response, weather forecasting and severe-weather operating processes.
Our customers reflect
For Tony Bascik today, looking back at the 12 months that KiwiRail services and State Highway 1 were closed brings back memories of a challenging time to be in the freight industry.
“Costs soared and the team had to handle extra hours and pressure to perform. I felt a sense of normality return when the line reopened, and we could go out and sell again. It seems so long ago now, and we have all moved on with more resilience in the network.
It’s very rare that we need to shut the line due to rock fall outages now when once this was common. The Kaikōura coastline is a unique and rugged coastline to have a rail line pass through it, so the engineering improvements have been wonderful.”
A critical freight connection remains
The Main North Line’s recovery is a reminder of the importance of resilient transport networks and of working closely with customers when the unexpected happens.
For customers, the legacy is simple: a vital freight route restored, a stronger corridor, and a more resilient rail network supporting business success.